The following is a tentative timeline for the procurement of Professional Design Services as the “Lead Design Firm.”
The dates below are estimates and subject to change.
- January 2025 - The Request for Qualifications is released and advertised.
- February/March 2025 - Statement of Qualifications submissions are evaluated and scored.
- March 12, 2025 - Announcement of the three shortlisted firms: BNIM, Hoefer Welker Architecture, and HDR Architecture.
- April 3 & 4, 2025 - Interviews/Presentations from the three qualified firms.
- April 2025 - Score the presentations.
- April/May 2025 - A Request for Proposal is issued.
- June 2, 2025 - Architect/Engineer Request for Proposal issued to Qualification Based on Selection 1, HDR Architecture.
- June 12, 2025 - Architect/Engineer Pre-Proposal Meeting.
- June 30, 2025 - Anticipated draft of proposal expected.
- Mid July 2025 - Anticipated Agreement executed.
- Early August 2025 - Anticipated Release for Request for Qualification for Construction Manager at Risk expected.
- October 3, 2025 - Design consultant contract fully executed.
- October 14, 2025 - A design kick-off meeting at the Center for Behavioral Medicine (CBM). After the kick-off, the first programming meeting began, which included the design contractor HDR, CBM’s programming team, University Health’s programming team and OA-FMDC’s project management team.
- November 4, 2025 - Closing on the land conveyed from Kansas City.
The official procurement documents may be viewed on the Office of Administration - Facilities Management Design and Construction Bid Listing webpage.